OUR WORK

Project Name

VRE

ROLE

Subcontractor
Interior Demolition & Site Preparation

Completed

December 2025

Project Overview

The VRE Project, locally known as the former YMCA facility, involved the renovation and conversion of an existing multi-level building into a climate-controlled storage facility. Build Logix Construction served as a subcontractor and performed comprehensive interior demolition across three levels, including the removal of walls, flooring, and ceilings. The scope of work also included the removal of all rooftop HVAC units, full debris removal, and final site cleanup. The project began in late October 2025 and was successfully completed in December 2025.